Purbachal Expressway & MRT Line 1, The Cost of Poor Infrastructure Coordination
Bangladesh spent about Tk10,329 crore developing the Purbachal Expressway from Kuril toward Kanchan. The wide corridor was designed to give eastern Dhaka a high-capacity road with main carriageways, service roads, underpasses and supporting infrastructure.
Then another megaproject arrived on almost the same corridor.
The Purbachal branch of MRT Line 1 will run roughly 11 kilometres from the Natun Bazar side toward Purbachal, with seven elevated stations. Much of its elevated structure will be built along the median of the newly developed expressway.
There is nothing wrong with putting metro rail beside a major road. The problem is that a road costing more than Tk10,000 crore reached completion before all the physical requirements of the metro construction had been fully absorbed into the same development programme.
The Road Will Have to Become a Construction Site Again
Early statements from metro authorities suggested that the expressway would not need to be broken because around three to four metres had been reserved in the median for MRT Line 1.
By February 2025, however, DMTCL confirmed that some sections of the expressway would have to be excavated and later repaired.
The construction plan includes:
metro piers along the central divider;
temporary use of around three metres on each side of the divider;
one main lane closed in each direction during parts of construction;
road surfaces opened at five intersections where underground water reservoirs conflict with piling;
construction of seven elevated stations;
restoration of affected road sections after the metro work is completed.
Three lanes in each direction are expected to remain usable. That means closing one of four main lanes reduces the nominal mainline lane count by 25% in each direction around active work zones, although actual traffic capacity will depend on how construction is managed.
This is exactly what better early coordination should try to avoid.
How Much Public Money Could Repeated Work Consume?
There is no reliable published figure yet for the final cost of repairing the expressway after MRT construction. Claiming that taxpayers will definitely lose a particular amount would therefore be misleading.
But the size of the road project shows why even limited rework matters.
The Purbachal Expressway cost approximately Tk10,329 crore. If future demolition, restoration, traffic management and associated rework were equivalent to only a small fraction of that investment, the numbers would still be significant.
These are not forecasts of the actual MRT-related damage bill. They simply show the financial scale: on a Tk10,329 crore project, even one percentage point represents more than Tk100 crore.
DMTCL has said the metro project will restore the areas it excavates. But that does not make the work free. Whether the money appears under the metro budget or another government account, reconstruction still uses public project resources.
People Also Pay a Cost That Does Not Appear in the Budget
The financial cost is only one side of the problem. The public was supposed to enjoy the benefit of a newly completed high-capacity road, yet portions of it must again operate as a construction corridor.
During metro construction, road users can face:
fewer usable lanes around work zones;
lower speeds near barriers and heavy equipment;
additional merging and lane-changing;
construction vehicles entering and leaving the corridor;
noise, dust and restricted roadside access;
unpredictable congestion around station construction sites.
The government argues that three main lanes on either side plus service roads should prevent severe disruption. That may be true under normal traffic levels.
But a road does not need to be completely blocked for construction to impose a cost. Ten extra minutes experienced by thousands of commuters every day becomes thousands of lost working hours, additional fuel use and lower productivity.
Those costs rarely appear in a project's headline budget.
Some Coordination Happened, But It Was Not Enough
It would also be wrong to say the two projects were planned with no coordination at all.
Authorities had left space in the central median for metro pillars and placed road lighting away from the middle. Metro planners also intend to use longer spans around underpasses so those structures do not have to be demolished.
The problem is that reserving space for pillars is not the same as integrating an entire metro project.
Stations require more space. Piling requires construction zones. Heavy machinery needs access. Some intersections contain underground reservoirs that must be opened for foundation work. Temporary barriers still occupy road space.
If the detailed MRT structures and construction requirements had been integrated while the expressway itself was being built, at least some of this repeated excavation, restoration and disruption could potentially have been reduced.
This Is What Unplanned Development Actually Costs
The Purbachal Expressway and MRT Line 1 are both useful projects. Dhaka needs high-capacity roads, but it also needs mass transit so every new neighbourhood does not depend entirely on private vehicles.
The failure is therefore not building one project instead of the other.
It is building two major pieces of infrastructure on the same corridor through separate construction cycles.
The result is simple:
Build the road → open the road → occupy parts of it again → excavate selected areas → construct the metro → repair the road again.
Every extra step consumes money, time and public patience.
Sustainable development is not only about how many expensive projects a country completes. It also means designing related projects together so that today's Tk10,000 crore investment does not become tomorrow's construction site before citizens have even received its full benefit.
The Purbachal corridor demonstrates that Bangladesh's infrastructure problem is sometimes less about a shortage of projects and more about a shortage of coordination between them.
0 Comments